Riverside Park Is Fenced Off Until 2027. Here's Where Roswell Still Gets to the River This Fall

October 22, 2026

The gates at 575 Riverside Road have been closed since February 1. Behind them, the City of Roswell is spending more than $13.8 million to rebuild the park that held Riverside Sounds, the sprayground, and generations of riverbank picnics. The City expects it to reopen in Summer 2027.

Riverside Park is one stop on a riverfront that Roswell is rebuilding park by park under its River Parks Master Plan, and the first stop the City finished is already open, just west along the same road. For the next several months, getting to the river in Roswell means using the newest part of that plan while the oldest part gets rebuilt.

The riverfront, stop by stop, as of October 2026

The City named two neighbors as alternate parking for the closure: Ace Sand Park and Don White Memorial Park. Azalea Park, the other City launch site, was left off that list.

Stop Address Status this fall
Riverside Park 575 Riverside Road Closed for renovation; reopening projected Summer 2027
Ace Sand Park 705 Riverside Road Opened November 2024; trails, fitness loop, Adventure Path
Don White Memorial Park 925(B) Riverside Road City-listed canoe and kayak launch, fishing docks, trails
Azalea Park 203 Azalea Drive City-listed canoe and kayak launch; NOC's Roswell base

The City says pedestrian routes around Riverside Park will stay open for the length of the project. It hasn't published a trail-specific detour, so if you walk the river path past the construction fence, check the signs on site before you plan a long out-and-back.

What the fence is hiding

Council approved a $12,299,308 construction contract with MAPP on December 8, 2025, and the total project budget is $13,841,187. According to the City, the work covers:

  • Accessible restrooms
  • A new pavilion and upgraded event space
  • A nature-based playground
  • A replacement sprayground
  • Circulation and accessibility improvements
  • Drainage and stormwater work
  • Security and lighting upgrades
  • New tree plantings

Crews broke ground on Friday, March 13, 2026. The money comes from the voter-approved 2022 Recreation & Parks Bond. At the ceremony, Mayor Pro Tem Sarah Beeson called the project one that "reflects our community's shared vision for investing in places that bring people together," as the City reported in Roswell Connections.

One part of the old routine is paused. According to the City's Riverside Park page, the Riverside Sounds concert series is on hold "until further notice."

The road outside the fence is next

The same stretch of Riverside Road that takes you to all four parks is headed into construction of its own. On July 13, Council approved a contract of just under $9.5 million with BackBone Infrastructure for the Riverside Road Corridor Improvement Project. Alongside it is a roughly $1.4 million Fulton County-funded waterline project.

The project covers about two miles between Riviera Road and Old Alabama Road. The finished corridor adds a roundabout at River Lake Drive, a new signal at Taimen Drive, raised medians, dedicated bike lanes, new sidewalks, and better pedestrian crossings.

The City's tree numbers tell you what the drive will look like during and after. The corridor holds 95 specimen trees. Of those, 23 will be removed and 72 will stay, about 76 percent. In all, 129 trees come out during construction and 49 new ones go in.

The City says construction starts after the contractor mobilizes and finishes pre-construction work. Once it does, expect what the City has told residents to expect: "periodic lane closures, temporary traffic shifts, and active work zones." The City says it will keep access to neighborhoods, businesses, schools, and parks open "whenever possible." It hasn't published a day-by-day closure calendar, so the project's updates on Roswell Connections are the place to check before you leave.

Ace Sand shows where the riverfront is headed

If Riverside was your default riverfront park, Ace Sand is the closest substitute. It also shows what the City is aiming for along the rest of the corridor. When it opened with a ribbon-cutting on November 6, 2024, the City called it the first project of the River Parks Master Plan, and Mayor Kurt M. Wilson described the plan as a blueprint for "a unified, first-class river park system," as reported in Roswell Connections.

Ace Sand sits just west of Don White Memorial Park. It cost about $2.2 million, paid for with City and federal ARPA funds. Here's what you'll find there:

  1. The fitness loop trail. A shaded, paved path along the river with fitness pods spaced along it.
  2. The Adventure Path. A woodland trail reached by smaller paths through the park's central grove of trees.
  3. The rock gardens by the sand volleyball courts. They look like landscaping, but they're bioswales that catch stormwater and let it soak into the ground to limit flooding and erosion.
  4. Native plantings. Thousands of them, there to help stabilize the riverbank.

Those stormwater features are the plan's main idea, and the Riverside contract follows the same approach with its drainage, stormwater, and tree-planting work. When Ace Sand opened, the City's next idea for the park was a Children's Stormwater Garden, meant to manage runoff while giving kids a place to learn and play. In other words, the plan treats the riverbank as something to repair as well as visit.

Getting onto the water

Riverside's canoe and kayak launch is behind the fence with everything else. The City lists two other launch sites, Don White Memorial Park at 925(B) Riverside Road and Azalea Park at 203 Azalea Drive. Besides the launch, Don White's City listing includes river access, fishing docks, trails, a volleyball court, and restrooms.

Nantahala Outdoor Center runs its Roswell outpost out of both parks. The National Park Service lists it as an authorized outfitter at the Azalea Drive address. NOC's Roswell kayak trips use the two parks as meeting points, either for an out-and-back paddle or a run between Don White and Azalea.

Timing matters here. NOC lists its Roswell kayak rentals for April through September, and stand-up paddleboard rentals through October. That means the listed SUP season ends with this month. Check NOC's Roswell outpost page for live availability before you drive over. If you have your own boat, the City launches don't depend on the rental calendar.

When you want water without a work zone

The same 2022 bond paying for Riverside also just finished a project well away from Riverside Road. The pond at Roswell Area Park reopened with a ribbon-cutting on Thursday, September 10, after nearly a year of construction and about $3.1 million in work.

Crews dredged the pond, rebuilt the embankment, upgraded the stormwater system, added new forebays, improved the retaining walls and the trail around the water, and planted 35 trees. Native and aquatic plants now line the edges, and logs were placed for turtles and other wildlife. The City reports that turtles and frogs started coming back before construction even wrapped up.

You can walk the trail around the pond, but leave the fishing rod at home. The City plans to add about 15,000 fish in phases as the pond settles, and expects fishing to resume in late summer or fall 2027. That's about when Riverside Park is due to reopen.

Roswell Area Park isn't finished with construction, either. On October 13, Council voted 5-0 to replace the playgrounds at four parks: East Roswell, Groveway Community, Roswell Area, and Sloan Street. The $1,542,117 contract went to Dominica Recreation Products. As Appen Media reported, the company will remove the old equipment, design the replacements, and install them. No closure dates have been announced, so if one of those four is your family's playground, watch Roswell Connections for notices.

For families with kids in fall soccer, one bond project is completely done. Fields 1 and 2 at Grimes Bridge Park switched from natural grass to artificial turf in a $4.1 million renovation and reopened with a ribbon-cutting on September 24. The City planned to plant 29 more trees there this fall.

Between now and Summer 2027, Roswell's river parks will look like this: Ace Sand and Don White open on one end of Riverside Road, Riverside rebuilding in the middle, and the road between them heading into its own construction.

At Cheever Home Group, we follow these projects because they shape everyday life near the river, from a weekend paddle to the drive home. If you're curious how the Riverside Road corridor and the River Parks Master Plan affect homes along this stretch of Roswell, get in touch and we'll walk you through what's finished, what's coming, and when.